Fee Schedule

This fee schedule applies to building permits, reviews, and miscellaneous fees.
Trade permits (Electrical, Mechanical, and Plumbing) have their own fee schedules listed within the application forms.

Building Department Fee Schedule PDF(PDF, 162KB)

Date Effective: 2024-04-23

We are currently using the FEBRUARY 2024 version of the ICC Building Valuation Data Table.  Decks are valued at $25 per sq. ft.

Building Permit Base Fee

Building Valuation Data (BVD)  Base Fee
Non-Refundable Application Fee $50
$1 to $2,000 $75
$2,001 to $10,000 $75 plus $8 per $1,000 over $2,000
$10,001 to $100,000 $165 plus $3 per $1,000 over $10,000
$100,001 to $500,000 $435 plus $2 per $1,000 over $100,000
$500,001+ $1,235 plus $3 per $1,000 over $500,000
Special / Additional Inspections $100 per Inspection

Notes: The base permit fee is rounded to the nearest whole dollar.

Inspections Included in Base Fee: Footing, Foundation, Backfill, Framing, Insulation, and Final.

 

Flat-Rate Residential Fees

Item Fee
Swimming Pools $100
Swimming Pool Barriers $100
Re-Roofing / Re-Siding (Each) $125
Demolition $125
Mobile Home Foundation Only $75
Mobile Home Setup (Applicable M/E/P permits must be obtained separately) $125
Window and Door Replacements (No change in size) $125
Solar Panel Installations $150

 

Flat-Rate Commercial Fees

Item Fee
Demolition Under 5,000 Sq. Ft. $125
Demolition Over 5,000 Sq. Ft. $125 + $0.07 per Sq. Ft. over 5,000 Sq. Ft.

 

Miscellaneous Fees

Item Fee
Large Format Copies
*Fees rounded to nearest whole dollar.
All Sizes (18x24, 24x36, 36x48):
<= 15 Pages: $2.00 / Page
> 15 Pages: $2.15 / Page
Standard Format Copies
*Fees rounded to nearest whole dollar.
All Sizes (8.5x11, 8.5x14, 11x17):
<= 10 Pages: No Charge
> 10 Pages: $0.10 / Page
Notice of Violation / Stop Work Order Posted $50
Certificate of Occupancy $50
Residential Temporary Certificate of Occupancy $1,000 Bond
Commercial Temporary Certificate of Occupancy $5,000 Bond
Shipping / Postage Costs Actual

 

Commercial Maintenance Annual Permit Fees

Item Fee
Annual Permit Set Up Fee $250
Per Inspection (1 Hour Maximum) $75

 

Commercial Plan Review Fees

We frequently engage third-party plan reviewers to complete commercial plan reviews, in-whole or in-part.  While we strive to ensure that our published plan review fees represent an accurate picture of the cost of a given plan review, we do not control the billing practices of our third-party reviewers.  It is our policy to bill no less than the actual cost incurred for a plan review performed by a third-party.

Building (Non-Structural) Base Plan Review Fees

Building Valuation Data (BVD) Base Plan Review Cost
$1 to $375,000 $450
$375,001 to $3,000,000 BVD * 0.0012
$3,000,001 to $6,000,000 $3,600 + ( ( BVD - 3,000,000 ) * 0.0005 )
$6,000,001+ $5,100 + ( ( BVD - 6,000,000 ) * 0.00035 )
Modifications to Base Fee:
Shell Building 20% Discount on Base Fee
Tenant Space Alterations when Previously Reviewed as Shell Building 50% Discount on Base Fee
 High Hazard Occupancies (Group H) Add 25% to Base Fee
Notes:
  • For mixed use occupancies, the BVD calculation is based on the primary function of the building.
  • Second reviews are included at no additional charge.
  • Third and later reviews are charged at a rate of $150.00 per hour.

 

Engineering Plan Review Fees

Item Plan Review Cost Minimum Fee
Structural 25% of Base Fee $375 
Mechanical 25% of Base Fee $375
Plumbing 25% of Base Fee $375
Electrical 25% of Base Fee $375
Energy Conservation 25% of Base Fee $375
Notes:
  • Second reviews are included at no additional charge.
  • Third and later reviews are charged at a rate of $150.00 per hour.

 

Fire Suppression Automatic Sprinkler System Review Fees

Number of Sprinkler Heads Plan Review Cost
1 to 15 $300
16 to 45 $455
46 to 100 $615
101 to 200 $760
201 to 300 $900
301 to 400 $1,050
401 to 500 $1,180
501+ $1,180 plus $1 per head over 500
 Notes:
  • Second reviews are included at no additional charge.
  • Third and later reviews are charged at a rate of $250.00 per hour.

 

Fire Alarm System Review Fees

Number of Alarm Devices Plan Review Cost
1 to 11 $300
12 to 45 $437
46 to 75 $575
76 to 100 $720
101 to 125 $865
126 to 150 $1,000
151+ $1,000 + $1.50 per device over 150
Notes:
  • Second reviews are included at no additional charge.
  • Third and later reviews are charged at a rate of $250.00 per hour.

 

Special Hazard Fire Suppression Systems - Wet Chemical Kitchen Hood

Number of Systems Plan Review Cost
1 $440
2 $580
3+ $580 + $115 / system over 2
Notes:
  • Second reviews are included at no additional charge.
  • Third and later reviews are charged at a rate of $250.00 per hour.

 

Special Hazard Fire Suppression Systems - Clean Agent / Carbon Dioxide / Similar

Pounds or Gallons of Suppression Agent Plan Review Cost
1 to 50 $440
51 to 100 $465
101 to 200 $525
201 to 300 $620
301 to 400 $700
401 to 500 $755
501 to 750 $825
751 to 1,000 $920
1,001+ $920 + $0.60 / pound over 1,000
Notes:
  • Second reviews are included at no additional charge.
  • Third and later reviews are charged at a rate of $250.00 per hour.