Phase 2

Sanitary Sewer Expansion - Westport Neighborhood

Please contact Public Works with any questions at publicworks@oshtemo.org or 269-216-5244.

Community Meeting Presentation(PDF, 3MB)

 

 

News/Updates

 5/28/26

Ashwood Dr is expected to be reopened on 5/29. More unsuitable soils must be removed than anticipated and that has slowed road building. 

Ramblewood Dr is expected to be restored up to Karabrooke Ct by end of day 5/29.

Work on Karabrooke Ct will begin Monday, 6/1. Residents should park on Winddrift until access is restored. Work is expected to take 3-4 days depending on soil conditions.

A new segment of pavement will be removed from Ramblewood starting on 6/2. There will still be access after the pavement is removed. Expect some delays during this activity.  

Ramblewood and Ashwood Dr are tentatively scheduled for base paving on 6/4. There will be intermittent disruptions to access during this activity. 

 5/27/2026 There is currently an isolated outage with Metronet fiber internet. There have been issues with the accuracy of the marking for communication lines. Redline is working with the MissDig contractor to resolve the issues and limit further disruptions. Service will be restored as soon as possible. 
 5/22/2026

Construction activities will be stopping for the week around 3 pm on Friday 5/22 in preparation for the holiday weekend. No work will be performed on Memorial Day. 

H Ave will be reopened the afternoon of Friday 5/22. Ramblewood Dr North of Ashwood Dr will have limited access restored for residents for the Holiday weekend. 

Work in the Ashwood Dr cul-de-sac will begin on Tuesday 5/26. Residents should plan to park their vehicles on Ramblewood Dr South of Ashwood Dr the evening of Monday 5/25. Access directly to driveways will be restored as soon as possible.

5/19/26

Redline has begun sanitary sewer install in Ramblewood Dr. Crews expect to reach the intersection of Ashwood Dr by end of day 5/20. Residents on Ramblewood will need to park South of construction while Ramblewood is rebuilt. Limited access from H Ave to driveways will be restored as soon as possible.

Residents may have received a wooden stake painted green at their front door. This is to mark the connection point for your home. If you need assistance, please contact Public Works or the onsite inspector from Fleis & Vandenbrink.

5/14/26

Redline Excavating will begin pavement removals on Ramblewood Dr starting at H Ave and working South on Friday, 5/15. Residents will retain access to their driveways during this work.

Sanitary sewer installation work is planned to begin on Monday, 5/18. The intersection of H Ave and Ramblewood Dr will be closed during this process and detours will be posted.

5/12/26 Redline Excavating has begun clearing on a Township parcel located at the end of Bluffton Ave. This area will be utilized for construction staging during the phase 2 project.
4/30/26 Informational meetings for Contract D (Westport North) are scheduled for May 9th from 11 am - 1 pm and May 13th from 4 pm - 6 pm. Post card invitations for these meetings are being mailed to each resident. Each meeting will feature a presentation on the construction schedule and impacts. There will be an opportunity for questions and answers after the presentation.
4/27/2026 The Township intends to award Contract D (Westport North) and E (Westport South) at the April 28th Township Board Meeting. Construction on Contract D is planned to begin this year, with Contract E planned for 2027. Invitations to informational meetings for residents in Contract D will be going out this week.
4/13/2026

Phase 2 bids were opened on April 1st. The Township received 1 bid for contract D, which is the North portion of Westport from Wyndham Dr and Torrington Rd North to H Ave. The contractor is Redline Excavating, who also completed Phase 1. The contract will now be conditionally awarded at the April 28th Township Board meeting and public meetings will be scheduled for May, with construction beginning in late May/early June.

The Township is working through a competitive re-bidding process for Contract C (Country Club Village) and Contract E (Westport South). Additional information will be available once re-bidding is completed.

3/24/2026 Consumers Energy plans to replace older gas service lines in the Phase 2 neighborhoods of Westport and Country Club Village. This work is separate from the sanitary sewer expansion projects and is expected to be completed beforehand. The Township is coordinating closely with Consumers Energy on these infrastructure upgrades to minimize disruptions for residents.
3/4/2026 Phase 2 projects are going to be advertised for bids starting on March 6th. Bids will be received through March 31st and opened at Township Hall on April 1st. The contracts are scheduled to be awarded at the April 14th Township Board meeting and neighborhood meetings will be scheduled shortly after. Postcards will be sent to all properties in the project areas with details on the neighborhood meetings.

 

Neighborhoods / Streets

Phase 2 has been updated to Westport North and South. Contract C will now be part of a future phase 3 project. 

Map of Westport: Contracts D & E (PDF, 1MB)

Contract D - Westport North

  • Ramblewood Dr
  • Windrift Ave
  • Maple Leaf Ave
  • Torrington Rd
  • Bramble Dr
  • Rose Arbour Ave
  • Chesapeake Dr
  • Cutty Sark Dr
  • Nightingale Ave
  • Signal Hill Dr
  • Wyndham Dr
  • Wild Cherry Ln
  • Walker Trail
  • Saybrook Dr
  • Countrywood Court
  • Karabrook Court
  • Ashwood Court
  • Chippendale Dr
  • Morningstar Way
  • Redbud Trail


 
      

Contract E - Westport South

  • Old Log Trail
  • Wild Cherry Ln
  • Killington Dr
  • Twilingate St
  • Wingate Rd
  • Thunder Bluff Rd
  • Litchfield Ln
  • Breezy Point Ln
  • Breckenridge Dr
  • Old Deer Run
  • Shugarbush Trail
  • Nantucket Ln
  • Rudgate Dr
  • Bunkerhill Dr
  • Valley Forge Rd
  • Cadet Ln
  • Trundel Ln
  • Brogan Hill
  • Sanfield Ln
  • Bluffton Ave


 


Construction Schedule

Construction is planned for Westport North in 2026 and 2027. Westport South will begin in 2027 and finish in 2028. 

  • 2026 Construction will begin at Ramblewood Dr and H Ave the week of May 18th. 
  • The contractor will be working from H Ave to the South until they reach the intersection of Ramblewood Dr and Torrington Ave. 
  • Construction will then move to Bramble Dr and H Ave and work South to the intersection of Bramble Dr and Rose Arbour Ave. 

Connection Process

 
Sanitary-Sewer-Connection-101-Flow-Chart.jpg

 

Sanitary-Sewer-Connection-101.jpg(PDF, 203KB)

There are two main steps each property owner must take to get connected to sanitary sewer once they have received the notice to connect.

  1. Pay Public Connection Fee: The total fee is $7,500 per residential property and is due before your contractor begins the physical connection. This fee can be financed with the Township through an installment payment agreement. More information on this agreement can be found in the resources section. 
  2. Hire Contractor for Private Connection: Be sure top get multiple quotes as prices and methods may vary. The township recommends getting multiple quotes for your connection. A few common connection methods are directional boring, open trenching, and rerouting interior plumbing. Costs are typically between $5,000 and $7,000. Financial help is available through USDA programs offering grants and low-interest loans, as well as township hardship financing and deferment options. Additional information on these options can be found in the resources section. 

Resources

Public Connection Fees can be financed through an installment payment agreement. There is a $500 down payment required and the remaining balance is financed over a 20- or 40-year term. For more information on installment payment agreements please contact Public Works or complete the form below to request an agreement for your property. 

For details and information on the assistance programs available for the Private Connection Fees please visit-

 

Once connected to sanitary sewer, the existing septic system will need to be properly abandoned. 

Contractor Information

Redline Excavating is a Michigan based contractor from Holland, MI.

The Consulting engineer is Fleis & Vandenbrink, an employee owned company. 

List of contractors for the private connection(PDF, 147KB)

Frequently Asked Questions

This FAQ will be updated throughout the project. If you have a question that is not listed below, please contact Public Works by phone at 269-216-5244 or email - publicworks@oshtemo.org

FAQ: What will this project cost me?

Answer: Connection costs have several components.

Public Connection Fee: $7,500 from the sewer main in the road to the right-of-way/property line

  • Benefit Fee: $2,000 for a single-family home (1 benefit unit) *commercial properties will have more benefit units.
  • Parcel Fee: $5,500 per parcel (same amount for all parcels, regardless of size or use).

Private Connection Fee: $5,000 to $7,000 from the right-of-way/property line to where the sewer exits the home.

  • Contact local excavating contractors for a quote.
  • Costs vary based on:
  • Distance from the home to the road.
  • Patios, decks, pools, fences, sheds, or other obstacles.
  • Tree removal (ask your contractor if trees can be avoided).
  • Location of existing interior plumbing.

FAQ: What are my payment options for the public connection fee?

Answer: You may pay the connection fee in full or enter a 40-year Installment Payment Agreement (IPA).

  • A $500 down payment is required.
  • The remaining $7,000 is financed at 3.375% interest.
  • Annual installments are paid with your winter tax bill.
  • There is no penalty for early payoff.

FAQ: When do I have to connect?

Answer: You will receive a notice once construction in front of your home is complete, including paving and testing. From the date on that notice, you will have two years to connect.

FAQ: How do I get connected?

Answer: Each property owner is responsible for hiring a contractor to connect the home to the new sanitary sewer. The Township website includes a list of contractors familiar with this work.

FAQ: Can I finance the private connection costs?

Answer: Most contractors do not offer financing, however:

  • Assistance programs may be available through the U.S. Department of Agriculture (USDA).
  • The Township offers a Hardship Assistance Program.

More details are available on the Township website.

FAQ: Are mailboxes being relocated?

Answer: Mailboxes may be temporarily relocated during construction but will remain on your property. The contractor will typically replace the mailbox post during reinstallation.
There may be temporary disruptions to mail delivery. USPS has the option to place a hold for mail pickup at the nearest post office.

FAQ: What will happen to my trash and recycling services?

Answer: Continue to place your trash and recycling at the end of your driveway as usual. If your regular provider cannot access your property, the contractor will collect trash. There may be delays in pickup, so please leave containers at the road until they are emptied.

FAQ: How will emergency services respond to my property if I need them?

Answer: Public Works coordinates with EMS daily during the project to ensure access plans are in place for properties directly affected by construction.

FAQ: How is my connection point determined?

Answer: Prior to construction in front of your property, the resident project representative will provide a wooden stake for you to mark the location. The inspector or Public Works can assist with marking the location.

FAQ: How will bus stops be affected by construction?

Answer: Public Works shares the project schedule and timeline with the Kalamazoo Public Schools Transportation Department. KPS will adjust bus stops as needed and will notify parents directly of any changes.

FAQ: Will my yard be restored?

Answer: Yes, the contractor will re-grade disturbed areas, place topsoil, and seed.
Restoration may occur in the following season, depending on when work along your property is completed.